Google Data Center Construction Stalled in Michigan Due to Permit Issues
Wayne County has issued a halt on the development of a Google data center in Van Buren Township, citing a lack of necessary permits as the primary reason for the stoppage.
In a stop work order dated Friday, Oladayo Akinyemi, the county’s Director of Public Services, detailed multiple concerns. He stated, “This construction activity is significantly impacting multiple county drains that are located on the construction site, including but not limited to work within the easement areas and obstructions within the drains,” and warned that the unauthorized work poses “significant risks of flooding.”
Matt Allen, a spokesperson for the county, confirmed to Michigan Public that work at the site has indeed been paused following the order, which was initially reported by MLive.
Known as “Project Cannoli,” the planned data center is anticipated to be enormous, consuming up to one gigawatt of power upon completion. This is comparable to the electricity usage of an entire city. In response to its energy needs, Google announced a collaboration with DTE in March to fund 2.7 gigawatts of capacity, investing in solar power and battery storage to balance its power consumption.
Will Conkling from Google emphasized the company’s commitment to covering its energy costs, stating in a blog post, “Google will fully cover its electricity costs and infrastructure needs, helping to ensure that its growth protects local ratepayers and actively bolsters the long-term resilience of the state’s electricity grid.”
However, the project faces scrutiny from Michigan Attorney General Dana Nessel, who filed a challenge against the Google-DTE agreement. She argued that the financial burden of supplying power to the center might unjustly fall on regular ratepayers, as reported in a filing last month.
Located near the junction of I-94 and I-275, just west of Detroit airport, the site had received final permits from the township by May, allowing construction to proceed through the fall. Despite this, the Wayne County Department of Public Services claims that the developer, Panattoni, failed to secure the required county-level construction permits.
The stop work order also noted that construction activities were found to be in violation of the county’s Stormwater Control ordinance, as they encroached on the county road’s right-of-way.
Akinyemi specified that construction must remain on hold until the developers obtain the necessary county construction permits and establish agreements with the county drain commissioner or relevant local drainage districts concerning stormwater runoff impacts.
In response, a Panattoni spokesperson assured compliance, stating, “We take compliance with applicable rules and regulations seriously. Coordination with local agencies is a part of the development process, and our team is working directly with county officials to review the items outlined, provide clarification where needed and work through the next steps.”
—